Bwindi Impenetrable Forest (01.01.2013 to 03.31.2013)

You are here

PDF versionPDF version
Year: 
2013
Quarter: 
January - March
Communications activities: 

No workshops held in Bwindi.

Unusual Events at the TEAM Site: 

No unusual events at the site

New Species: 

No species recorded at site

Protocol Activities: 

All the six vegetation plots were re-measured. The data was submited in to the portal. All monthly weather dat also submitted.

Protocol Problems: 

No problems related to standard protocol implemementation.

Schedule Problems: 

No schedule problems, all activities inplemented on scehdule.

Logistical Problems: 

No logistical problems at site.

Suggestions: 

Statistics and Data analysis training for site managers. This will allow increased peer-reviewed publication rate from the network.