Nouabalé Ndoki (07.01.2015 to 09.30.2015)

You are here

PDF versionPDF version
Year: 
2015
Quarter: 
July - September
Communications activities: 

Brief meeting with the new manager of the Nouabale Ndoki National Park to explain them about the TEAM project

Unusual Events at the TEAM Site: 

None

New Species: 

None

Protocol Activities: 

 

Three activities occur in the NNNP as part of TEAM Protocol: VG, CT and CL

 

 

No VG activities this trimester

 

CT data are not yet uploaded to the TEAM depository because we have problems to create a TPK file. We are in contact with the TEAM Network Technical & Communication Manager to find a solution

 

CL data are uploaded on the TEAM portal

Protocol Problems: 

None

Schedule Problems: 

None

Logistical Problems: 

None

Suggestions: 

None